Super Trishuli Hydro Power Project
- Approvals available for Construction license, Grid connection, Power purchase agreement (PPA) and Environmental impact Studies.
- Pre-qualification for Civil & Hydro Mechanical works floated in October 2018, bids under evaluation.
- Pre-qualified contractors for this package will submit bids.
- Selection of Owners engineer (OE) for the Design Engineering Review and construction supervision etc. expected to be awarded shortly.
- Arrangement for the project funding is being planned with debt/ equity ratio of 75% (NPR 1200 Crore) and 25% (NPR 400 Crore), respectively.
- The financial closure is expected by December 2019.
- Blue Energy is considering proposal from competent E-M vendors/EPC Contractors with the proposal to fund E-M part of the project.
- PQ for Electro-mechanical package, shortly.
- The Super Trishuli Project construction is tentatively scheduled to commence on January 2020, commissioning likely by Feb 2024.
- PPA with NEA envisages RCOD by Feb 2024.